Last updated 8 March 2017
Construction of the PopUp will begin in March 2017, with vendors and services transitioning to the new space in late May and early June before the mid-year opening.
MARCH
Week 1 – Week 2: Site Establishment
- Fencing established
- Tree protection and removal
- Demountable building demolition
- New pedestrian paths in place
This will be one of the noisiest periods in the PopUp construction, as heavy machinery is brought in to demolish demountable buildings and remove vegetation. Wayfinding signage will be in place to direct pedestrian traffic around the site.
Week 2 – 4: Fit Out
- Demolition continues
- Footing system established
Construction will sound like a house being built as the footings for the PopUp are established. This stage of the project involves some drilling and hammering.
Week 4 – Week 6: Flooring
- Flooring, wall frames and trusses
As the largely timber structure is established noise from the construction will mainly be produced by power tools.
APRIL
Week 6 – Week 8: Roofing
- Roofing, services, rough-in & façade
- Decking flooring complete
As structures and flooring are finalised noise from the construction will mainly be hammering.
Week 8 – Week 10: Fit Out
- Plaster boarding
- Façade and wall finishes
- Services fit out
As construction moves to the internal fit out, intermittent sounds of hammers will be audible as fit out materials are installed.
MAY
Week 10– Week 12: Services and landscaping
- Finalise fit out
- External services connection
- Landscaping
The PopUp will enter the final stages of construction and smaller amounts of noise will be audible. As services are connected to the PopUp, there may be minor disruption to power, water and other services. Where possible interruptions will be planned for after hours to minimise disruption.
Week 12 – Week 14: Commissioning and Building Certification
- Continuation landscaping
- Services commissioning
- Building certification
- Tenancy fit-out
Noise and disruption will be limited. Vendors will begin transitioning and fitting out their PopUp shopfronts.
JUNE
Week 14 – Week 16: Transition to Operations
- Continuation of tenancy fit-out
- Copland shed and services installation
- Walkways open
The PopUp site will commence operation. Fences will be removed and pedestrians will be able to move freely through the PopUp Village.